| Project Description: |
BOSTON- BRIDGE PRESERVATION, B-16-222 (3F3), JAMAICAWAY OVER STATE ROUTE 9/HUNTINGTON AVENUE
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Alina Daragan![]() |
| Estimated Total Contract Cost: | $10,220,000.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 6 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
||||||
|
|
|
||||||||||||||||||||