FOXBOROUGH- MIDDLEBOROUGH- NORTON- BRIDGE PRESERVATION ALONG I-495, F-06-023, M-18-042, M-18-043, N-23-026, N-23-027 & N-23-034
This project will consist of Bridge Preservation at several bridge crossings in the I-495 corridor. The locations are the Spruce Street bridge (Foxborough), the Vernon Street bridge (Middleborough), the Cherry Street bridge (Middleborough), the N. Washington Street bridge (Norton), the Newcomb Street bridge (Norton), and the Plain Street bridge (Norton).
Location:
  • Town of Foxborough
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2026/2027
    Project Manager: Albin Napit
    Estimated Total Contract Cost: $10,853,198.23
    Estimated Total Federal Participating Construction Cost: $11,142,899.96
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 5
    Current Status: Final Package to FAPRO (as of 09/04/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: FOXBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Added via STIP action 11.
  • Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $9,061,732.00
    State Cost: $2,265,433.00
    Total Cost: $11,327,165.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/24/2025
    Project Initiation Form PIF Entered 11/24/2025
    Project Initiation Form PRC Submitted 11/26/2025
    Project Review Committee PRC Approved 12/16/2025
    Project Management
    75% Design 75% Package Received 06/30/2026
    75% Design 75% Package Comments to DE 08/03/2026
    Final Design PS&E Received 08/19/2026
    Final Design PS&E to FAPRO 09/04/2026