| Project Description: |
MIDDLEFIELD- SUPERSTRUCTURE REPLACEMENT, M-19-002, M-19-003, AND M-19-004, TOWN HILL ROAD BRIDGES OVER FACTORY BROOK
|
| Location: |
|
| Design Responsibility: | Consultant |
| Project Manager: | Robert N Rottenbucher![]() |
| Estimated Total Contract Cost: | $20,997,900.00 |
| Estimated Total Federal Participating Construction Cost: | $21,775,600.00 |
| District: | District 1 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
||||||
|
|
|
||||||||||||||||||||