Project Description:
BOSTON- INSTALLATION OF NOISE BARRIERS ALONG I-90 BETWEEN MARKET AND FRANKLIN STREETS (ALLSTON MULTIMODAL TRANSPORTATION PROJECT EARLY ACTION)
MassDOT is proposing two noise barriers along the westbound lanes of I-90 near Lincoln Street, from Market Street to Franklin Street to mitigate highway traffic noise for nearby residences.The barrier is located entirely within the MassDOT State Highway Layout (SHLO) and designed to enable the City of Boston’s long-term plans for a shared-use path connection through the Allston-Brighton corridor. The design provides adequate clearance for a future Shared Use Path within the SHLO, ensuring that construction of the barrier will not preclude or complicate future City-led mobility improvements.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2026/2027
    Project Manager: Susan Harrington
    Estimated Total Contract Cost: $23,394,413.40
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 09/26/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/26/2026
    Project Initiation Form PIF Entered 02/27/2026
    Project Initiation Form PRC Submitted 02/27/2026
    Project Review Committee PRC Approved 03/04/2026
    Project Status Advertised 09/26/2026
    Project Management
    100% Design 100% Package Received 06/26/2026
    25% Design 25% Package Received 06/09/2025
    75% Design 75% Package Received 12/12/2025
    Final Design PS&E Received 09/01/2026
    Final Design PS&E to FAPRO 09/21/2026