AMHERST- SUNDERLAND- PAVEMENT PRESERVATION ON SR116 (MM 24.06-28.70)
The work to be completed under this contract consists of two pavement treatments on Route 116 in the Towns of Amherst and Sunderland. The first treatment is roadway milling, resurfacing, and crack sealing for approximately 3.6 miles starting at the southern limit of the project. The second treatment is crack sealing only for approximately 1 mile starting at the northern limit of the project. The project begins at the pavement joint approximately 173 ft north of Route 116/Meadow Street intersection (mile marker 23.76) and ends at the pavement joint approximately 468 ft south of Route 116/47 intersection in Sunderland (mile marker 28.39). The length of the project is 4.6 miles. The contract specified thickness for milling and HMA resurfacing is designed to maintain the existing roadway surface elevation. Field changes which will alter the final pavement elevation must be approved by the Engineer. The work also includes replacement of dated guardrail, removal of built-up material on shoulders to restore country drainage, adjusting and/or rebuilding drainage structures, installing recessed pavement markings and slotted pavement markers, implementing temporary traffic controls, and other incidental items as set forth in the proposal and required to complete the work.
Location:
  • Town of Amherst
  • Town of Sunderland
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2027
    Project Manager: Eric I Nova
    Estimated Total Contract Cost: $4,979,722.17
    Estimated Total Federal Participating Construction Cost: $5,326,564.18
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the STATEWIDE.
    District: District 2
    Current Status: PS&E Received (as of 10/02/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: AMHERST
    SUNDERLAND
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $5,026,450.40
    State Cost: $1,256,612.60
    Total Cost: $6,283,063.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/27/2026
    Project Initiation Form PIF Entered 03/02/2026
    Project Initiation Form PRC Submitted 03/02/2026
    Project Review Committee PRC Approved 03/04/2026
    Project Management
    100% Design 100% Package Received 08/05/2026
    100% Design 100% Package Comments to DE 09/07/2026
    75% Design 75% Package Received 08/05/2026
    Final Design PS&E Received 10/02/2026