| Project Description: |
GREENFIELD- BERNARDSTON- PAVEMENT PRESERVATION ON US5 AND SR10 (MM 43.77-53.50)
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Spring 2027 |
| Project Manager: | Eric I Nova![]() |
| Estimated Total Contract Cost: | $8,165,669.10 |
| Estimated Total Federal Participating Construction Cost: | $8,163,860.65 |
| District: | District 2 |
| Current Status: | 75% Package Received (as of 08/11/2026 ) |
|
Bridges |
||||||
|
|
|
||||||||||||||||||||||||||