| Project Description: |
WILLIAMSBURG- CLEANING AND PAINTING OF STEEL, W-36-015, STATE ROUTE 9 OVER WEST BRANCH OF THE MILL RIVER
The scope of this bridge maintenance project is focused on painting the structural steel members of Bridge W-36-015, which carries Route 9 over the West Branch of the Mill River. The bridge was built in 2002 and is comprised of weathering steel.
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Spring 2027 |
| Project Manager: | Alina Daragan![]() |
| Estimated Total Contract Cost: | $600,379.50 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 1 |
| Current Status: | PS&E Received (as of 10/22/2026 ) |
|
Bridges |
||||||
|
|
|
||||||||||||||||||||||||||||||||||||||