| Project Description: |
MILFORD- INTERSECTION IMPROVEMENTS AT ROUTE 109/BEAVER STREET AND I-495 (SB) OFF-RAMP
The project will improve safety and operations at the intersections of Route 109 (Medway Road) with Beaver Street and the I-495 SB ramps (Exit 48).
|
| Location: |
|
| Design Responsibility: | Municipality |
| Project Manager: | Janhavi Limaye![]() |
| Estimated Total Contract Cost: | $6,981,750.00 |
| Estimated Total Federal Participating Construction Cost: | $7,462,762.50 |
| District: | District 3 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges |
||||||
|
|
|
||||||||||||||||||||