| Project Description: |
DISTRICT 5- ROOFING UPGRADES AND STRUCTURAL REPAIRS TO CHEMICAL STORAGE SHEDS
Work shall roofing upgrades and structural repairs to deteriorated/damaged schemical storage sheds
|
| Location: | |
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Terence Roche![]() |
| Estimated Total Contract Cost: | $3,000,000.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 5 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges |
||||||
|
|
|
||||||||||||||||||||