| Project Description: |
DISTRICT 3- SCHEDULED & EMERGENCY BRIDGE DECK AND JOINT REPAIRS AND RELATED WORK AT VARIOUS LOCATIONS ALONG I-90
The work will consist of scheduled and emergency bridge deck repairs and related work at various locations on I-90 within District 3.
|
| Location: | |
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Spring 2027 |
| Project Manager: | Patrick Yum![]() |
| Estimated Total Contract Cost: | $1,300,984.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 3 |
| Current Status: | 100% Package Received (as of 10/20/2026 ) |
|
Bridges |
||||||
|
|
|
||||||||||||||||||||||||||||||||