| Project Description: |
WORCESTER- BRIDGE PRESERVATION, W-44-109 (1T0 & 1T1), I-290 OVER COMB RAMP AND P&W RAILROAD
The work will consist of steel repairs, cleaning and painting of structural steel, and other related work on Bridge No. W-44-109 (1T0 & 1T1), carrying I-290 over Comb Ramp and the P&W Railroad in Worcester.
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Albin Napit![]() |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 3 |
| Current Status: | This project is in the preliminary design phase. |
|