UXBRIDGE- BRIDGE MAINTENANCE AND PRESERVATION, U-02-014 (1J3 & CDU), HECLA STREET OVER WEST RIVER & ABANDONED CANAL
This project will consist of various types of Bridge Preservation work at the Hecla Street arch bridge in Uxbridge, over the West River and an abandoned canal.
Location:
  • Town of Uxbridge
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2027
    Project Manager: Dylan Brown
    Estimated Total Contract Cost: $4,543,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/28/2026
    Project Initiation Form PIF Entered 07/28/2026
    Project Initiation Form PRC Submitted 07/28/2026
    Project Review Committee PRC Approved 07/29/2026
    Project Management