| Project Description: |
PEABODY- DECK REPLACEMENT, P-03-027, DEARBORN ROAD OVER US-1 N (RAMP C)
This project will replace the deck on the bridge carrying Dearborn Road over the ramp connecting I-95/Rte 129 to US-1 Northbound in the City of Peabody.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Kelsey Munns![]() |
| Estimated Total Contract Cost: | $3,910,344.82 |
| Estimated Total Federal Participating Construction Cost: | $4,199,999.99 |
| District: | District 4 |
| Current Status: | This project is in the preliminary design phase. |
|