Project Description: |
DEDHAM- BRIDGE REPLACEMENTS, D-05-029, PROVIDENCE HWY OVER HIGH & HARRIS STS & D-05-030, PROVIDENCE HWY OVER HARRIS ST.
This project will result in the replacement of the Providence Highway (formerly Route 1) bridge over High Street and the Providence Highway over Harris Street bridge with one bridge over both streets. The construction will be staged to maintain two lanes northbound and one lane southbound at all times. Reconstruction of the High Street/East Street intersection is also included.
|
Location: |
|
Resident Engineer: | Eric Zilinsky |
Construction Contract Value: | $16,825,011.83 |
Construction Bid Price: | $14,315,649.35 |
Initial Construction Estimate: | $13,522,198.00 |
District: | District 4 |
|
Bridges
|
|
|
|
|