Project Description:
EASTHAMPTON- BRIDGE REPLACEMENT, BR# E-05-004 ROUTE 5 OVER THE MANHAN RIVER
Location:
  • Town of Easthampton
  • Resident Engineer: Jim Hoey
    Construction Contract Value: $3,183,633.22
    Construction Bid Price: $3,125,633.22
    Initial Construction Estimate: $3,287,000.00
    District: District 2
    Current Status: Physical work completed. (as of 11/16/2004)

    Contracts (1) Progress
    # 32301 -- Construction Contract
    Bridge Replacement E-5-4 (Steel)- Route 5 over The Manhan River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/23/2002
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work completed.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/13/2001
    Project Status Advertised 10/20/2001
    Project Management