Project Description: |
SOMERSET- SWANSEA- BRIDGE REPLACEMENT, S-16-003=S-35-003, ROUTE 103 (WILBUR AVENUE) OVER THE LEE RIVER
The proposed project consists of replacing the existing Wilbur Avenue bridge over the Lees River in its present location with minor improvements to the approach roadways. A traffic detour will be in place during construction.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Martin Leelman![]() |
Estimated Total Contract Cost: | $2,383,988.00 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|