Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SOMERSET- SWANSEA- BRIDGE REPLACEMENT, S-16-003=S-35-003, ROUTE 103 (WILBUR AVENUE) OVER THE LEE RIVER
The proposed project consists of replacing the existing Wilbur Avenue bridge over the Lees River in its present location with minor improvements to the approach roadways. A traffic detour will be in place during construction.
Location:
  • Town of Somerset
  • Town of Swansea
  • Resident Engineer: Rajat Gogoi
    Construction Contract Value: $2,383,988.00
    Construction Bid Price: $2,129,328.00
    Initial Construction Estimate: $1,161,000.00
    District: District 5

    Contracts (2) Progress
    # 52513 -- Construction Contract
    Somerset - Swansea - Bridge Replacment (S16-003=S-35-003) Rte 103 (Wilbur Avenue) over the Lee River Completed
    # 94469 -- Design -- Footprint Bridge contracts
    CONTA FTPRT-RD2 FA NON-NHS STP Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/08/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 08/20/2005
    Project Status Advertised 09/23/2006
    Project Management
    100% Design 100% Package Received 05/16/2005
    100% Design 100% Package Comments to DE 06/28/2005
    25% Design 25% Package Received 10/14/1999
    25% Design 25% Package Comments to DE 06/25/2001
    25% Design 25% Package Approved 04/30/2004
    25% Design Design Public Hearing 04/29/2004
    25% Design 25% Plans Complete 04/29/2004
    75% Design 75% Package Received 12/01/2004
    75% Design 75% Package Comments to DE 03/10/2005
    75% Design 75% Plans Approved 03/10/2005
    75% Design 75% Plans Complete 03/10/2005
    Final Design PS&E Received 08/16/2005
    Final Design PS&E to FAPRO 08/16/2005
    Consultant Contract Process Scope to DE 11/20/1996
    Consultant Contract Process NTP Issued 12/23/1997
    Consultant Contract Process Workhours Approved 12/17/1997