Project Description:
AMHERST- SOUTH HADLEY- RECONSTRUCTION & RELATED WORK ON ROUTE 116 (WEST STREET)
This project on Route 116 begins at a point 831 feet south of the Amherst/Granby/South Hadley Town Line and extends to a point 525 feet north of Country Corners Road, for a project length of approximately 1.20 miles. This roadway section has been a concern due to the steep slope and curvy terrain of the current alignment. This project will improve the roadway alignment, will include two new left-turning lanes, and provide shoulders and a complete drainage system.
Location:
  • Town of Amherst
  • Resident Engineer: Thomas Kozik
    Construction Contract Value: $3,506,513.00
    Construction Bid Price: $3,128,937.90
    Initial Construction Estimate: $3,354,684.00
    District: District 2

    Contracts (3) Progress
    # 54619 -- Design -- Geotechnical
    Work will consist of laboratory and field testing, subsurface investigation inspection and design and analysis of complex foundation rehabilitation projects. Final
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 74038 -- Construction Contract
    Reconstruction and Related Work (Including Rock Fall Containment) on a Section of Route 116 (West Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/04/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/04/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 10/23/2009
    Project Status Advertised 06/23/2012
    Project Management
    100% Design 100% Package Received 04/28/2011
    100% Design 100% Package Comments to DE 08/26/2011
    25% Design 25% Package Received 04/13/2009
    25% Design 25% Package Comments to DE 08/19/2009
    25% Design Design Public Hearing 03/16/2010
    75% Design 75% Package Received 07/14/2010
    Final Design PS&E Received 06/04/2012
    Final Design PS&E to FAPRO 06/20/2012