Project Description:
CHICOPEE- HOLYOKE- BRIDGE REHABILITATION, C-13-012=H-21-030, ROUTE 116 (CHICOPEE/CABOT ST) OVER CONNECTICUT RIVER & PV RR (AKA WILLIMANSETT BRIDGE)
The purpose of this project is to rehabilitate the existing bridge through the replacement of the bridge deck, sidewalks, and historic metal bridge railings. The existing bridge support structure will be repaired and strengthened and all structural steel will be repainted. A detour will be required during construction. The highway work will be limited to approach roadway work.
Location:
  • City of Chicopee
  • City of Holyoke
  • Resident Engineer: Joseph Gaudet Jr
    Construction Contract Value: $27,634,611.67
    Construction Bid Price: $19,257,704.00
    Initial Construction Estimate: $28,674,663.75
    District: District 2

    Contracts (9) Progress
    # 54821 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 54833 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 55545 -- Design -- Bridge Open End
    Work will consist of reviewing Bridge Project estimates and preparing guidance for estimating of Bridge projects. Final
    # 57598 -- Design -- Hwy Eng Open End
    Work will consist of providing design and engineering services to MassHighway on a task order basis for various statewide Value Engineering Studies. Final
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 58213 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64317 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68202 -- Construction Contract
    Willimansett Bridge Deck Replacement and Related Work (Including Painting) (C-13-012-=H21-030) (Steel) – Route 116 (Cabot Street) over the Connecticut River and the Pioneer Va Completed
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/29/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/18/2010
    Project Management
    100% Design 100% Package Received 04/14/2010
    25% Design 25% Package Received 12/11/2007
    25% Design 25% Package Comments to DE 09/08/2008
    25% Design Design Public Hearing 04/16/2009
    75% Design 75% Package Received 11/10/2009
    75% Design 75% Package Comments to DE 12/18/2009
    Final Design PS&E Received 08/24/2010
    Consultant Contract Process Scope to DE 05/20/2002
    Consultant Contract Process NTP Issued 05/21/2004
    Consultant Contract Process Workhours Approved 12/16/2003