Project Description:
MILLBURY- BRIDGE REPLACEMENT, M-22-005, ROUTE 122A OVER THE BLACKSTONE RIVER
The work under this project consists of the replacement of the Route 122A Bridge (N. Providence Road) over the Blackstone River. The proposed bridge will be a single span concrete box girder bridge with a cast-in-place concrete deck. New abutments will be constructed behind the existing abutments. The steel piles will be rock socketed into ledge. A handicap accessible sidewalk will be provided on both sides of the bridge. The width of the proposed bridge will be approximately the same as the existing bridge. The existing wingwalls will be replaced with concrete wingwalls of approximately the same lengths at the four corners of the bridge. The roadway between Canal Street and Maple Street will be fully reconstructed. The existing vertical and horizontal roadway alignment will be maintained. The bridge will be closed during construction and a detour route will be established. The project also includes the demolition of one building/dwelling.
Location:
  • Town of Millbury
  • Resident Engineer: Stephen Shamoian
    Construction Contract Value: $2,967,954.00
    Construction Bid Price: $1,245,560.90
    Initial Construction Estimate: $1,397,055.00
    District: District 3
    Current Status: All of the contaminated material has been removed and shipped off site. The pile driving results are being reviewed by the Geotechnical department. Unexpected subsurface obstructions were encountered which prohibit the installation of the steel piles. The project is being reviewed for options. (as of 11/21/2008)

    Contracts (2) Progress
    # 65444 -- Construction Contract
    Bridge Replacement (M-22-005) (Concrete) - Route 122A (North Providence Road) over the Blackstone River. (RE-ADVERTISED) Completed
    # 96054 -- Design -- Bridge Open End
    RD 3 F/A NON-NHS BRIDGES-CON E Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/14/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    All of the contaminated material has been removed and shipped off site. The pile driving results are being reviewed by the Geotechnical department. Unexpected subsurface obstructions were encountered which prohibit the installation of the steel piles. The project is being reviewed for options.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 06/24/2006
    Project Status Advertised 07/03/2010
    Project Management
    100% Design 100% Package Received 11/09/2005
    100% Design 100% Package Comments to DE 01/31/2006
    25% Design 25% Package Received 08/06/2003
    25% Design 25% Package Comments to DE 12/24/2003
    25% Design Design Public Hearing 03/24/2004
    75% Design 75% Package Received 01/20/2005
    75% Design 75% Package Comments to DE 03/09/2005
    Final Design PS&E Received 05/11/2006
    Final Design PS&E Received 04/09/2010
    Final Design PS&E to FAPRO 05/24/2006
    Final Design PS&E to FAPRO 05/19/2010
    Consultant Contract Process NTP Issued 08/10/2001