Project Description:
FRAMINGHAM- ROADWAY RECONSTRUCTION AND RELATED WORK ON SECTIONS OF ROUTE 126 (CONCORD STREET) AND ROUTE 30 (COCHITUATE ROAD)
The work under this contract consists of signal and roadway improvements at the Intersection of Route 126 (Concord Street) and Route 30 (Cochituate Road) in the Town of Framingham. The work includes traffic signal improvements, unclassified excavation, full depth bituminous concrete pavement reconstruction, and overlay, drainage improvements, installing new granite curb, cement concrete sidewalks and bituminous driveways and walkways, construction of retaining walls, traffic signs, and new pavement markings.
Location:
  • Town of Framingham
  • Resident Engineer: George Berte
    Construction Contract Value: $1,744,118.10
    Construction Bid Price: $1,527,218.10
    Initial Construction Estimate: $1,641,849.00
    District: District 3

    Contracts (1) Progress
    # 33236 -- Construction Contract
    Roadway Reconstruction and Related Work on Sections of Route 126 (Concord Street) and Route 30 (Cochituate Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/01/2003
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/28/2002
    Project Management