Project Description:
LINCOLN- BRIDGE REPLACEMENT, L-12-002, CONCORD ROAD (ROUTE 126) OVER MBTA
The purpose of this project includes reconstruction of the bridge substructure and superstructure, full depth roadway reconstruction, and full depth reconstruction of the multiuse path on the north side of the bridge. The bridge will be raised approximately 3 feet to provide a minimum of 21-foot clearance for double deck trains.
Location:
  • Town of Lincoln
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2025
    Project Manager: Eamon Kernan
    Estimated Total Contract Cost: $10,118,656.15
    Estimated Total Federal Participating Construction Cost: $10,524,545.98
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 75% Package Comments to DE (as of 01/22/2024 )

    Contracts (2) Progress
    # 115757 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77856 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: LINCOLN
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $9,779,636.80
    State Cost: $2,444,909.20
    Total Cost: $12,224,546.00

    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/01/2007
    Project Review Committee PRC Approved 06/12/2008
    Project Review Committee Letter 07/16/2008
    Project Status Initiated 02/22/2006
    Project Management
    25% Design 25% Package Received 09/02/2021
    75% Design 75% Package Received 12/15/2023
    75% Design 75% Package Comments to DE 01/22/2024
    Consultant Contract Process NTP Issued 01/15/2018