Project Description:
DANVERS- RECONSTRUCTION OF TWO INTERCHANGES ON ROUTE 128, WITH ROUTE 62 AND ROUTE 128 WITH ROUTE 35, INCLUDES REPLACEMENT OF D-03-020 (PHASE I)
This purpose of this project is to construct new acceleration/deceleration lanes at the Route 35 (High Street) and Route 62 (Elliot Street) interchanges. The project also proposed to replace the bridge carrying Route 128 over an unused MBTA rail road located south of the High Street interchange.
Location:
  • Town of Danvers
  • Resident Engineer: Susan Cranney
    Construction Contract Value: $27,591,539.44
    Construction Bid Price: $20,147,249.16
    Initial Construction Estimate: $27,183,217.00
    District: District 4

    Contracts (3) Progress
    # 51301 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57731 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 60072 -- Construction Contract
    Roadway Reconstruction on a Section of Route 128 Including Replacement of Bridge (D-03-020) (Steel). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/04/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 07/25/2009
    Project Management
    100% Design 100% Package Received 02/09/2007
    100% Design 100% Package Comments to DE 09/17/2007
    25% Design 25% Package Received 01/02/2002
    25% Design Design Public Hearing 06/24/2004
    75% Design 75% Package Received 01/07/2005
    75% Design 75% Package Comments to DE 06/26/2006
    Final Design PS&E Received 07/06/2009
    Final Design PS&E to FAPRO 07/09/2009
    Consultant Contract Process NTP Issued 12/20/2000
    Consultant Contract Process Workhours Approved 08/22/1997