Project Description:
DANVERS- RECONSTRUCTION OF TWO INTERCHANGES ON ROUTE 128, WITH ROUTE 62 AND ROUTE 128 WITH ROUTE 35, INCLUDES REPLACEMENT OF D-03-020 (PHASE I)
This purpose of this project is to construct new acceleration/deceleration lanes at the Route 35 (High Street) and Route 62 (Elliot Street) interchanges. The project also proposed to replace the bridge carrying Route 128 over an unused MBTA rail road located south of the High Street interchange.
Location:
  • Town of Danvers
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Steven E McLaughlin
    Estimated Total Contract Cost: $27,591,539.44
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • D03020 
    See the Milestone Details tab for additional Project information