Project Description:
CANTON- DEDHAM- NORWOOD- INTERCHANGE IMPROVEMENTS AT I-95/I-93/UNIVERSITY AVENUE/I-95 WIDENING INCLUDING 10 BRIDGES AND 9 MULTI-USE PATH/PEDESTRIAN BRIDGES
The I-95/I-93/University Avenue Interchange Improvement Project is divided into two distinct sections. The I-95/I-93/University Avenue Interchange section extends along I-93 southbound from just west of the I-93/Route 138 Interchange out to the University Ave entrance ramp on I-95 northbound. Work in this area includes: • Replacement of the I-95 northbound clover leaf ramp with a high speed, two lane, direct connect ramp. • A realigned and improved high speed two-lane, direct connect between I-93 southbound and I-95 southbound. • A new entrance ramp from University Avenue to I-93 northbound along the Green Lodge Street ROW. This includes discontinuance of Green Lodge Street west of Elm Street. • A new exit ramp from I-93 southbound to University Ave. The other section of the project is south of the I-95/I-93 Interchange and includes. • The construction of a fourth lane, for two miles in the median, of I-95 southbound from the I-95/I-93 Interchange to Neponset St. • The construction of a fourth lane, for one mile in the median of I-95 northbound, from Dedham St to the I-93 on ramp.
Location:
  • Town of Canton
  • Town of Dedham
  • Town of Norwood
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $202,205,993.90
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: 25% Package Comments to DE (as of 09/10/2014 )

    Contracts (4) Progress
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 57735 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Received 07/14/2011
    Project Need Form PNF Entered 07/14/2011
    Project Need Form PNF Approved 07/14/2011
    Project Initiation Form PIF Received 07/14/2011
    Project Initiation Form PIF Entered 07/29/2011
    Project Initiation Form PRC Submitted 08/01/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/22/2011
    Project Status Initiated 10/20/2005
    Project Management
    25% Design 25% Package Received 07/25/2014
    25% Design 25% Package Comments to DE 07/23/2014
    25% Design 25% Package Comments to DE 09/10/2014