Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CANTON- DEDHAM- RANDOLPH- WESTWOOD- RECONSTRUCTION ON ROUTE 128 (I-93 ADD-A-LANE) FROM ROUTE 24 (RANDOLPH) TO EAST STREET ROTARY (WESTWOOD) (ROADWAY I) INCLUDES D-05-W31, M-25-030, R-01-010
This contract consists of approximately 5 miles of I-95/93 (Route 128) roadway construction, beginning at Route 24 (Randolph) to the MBTA Franklin Rail Road Line bridge in Westwood, just north of the East Street Rotary. An additional 12-foot travel lane and 10-foot shoulder will be constructed toward the median in both directions. Construction will also consist of retaining walls, drainage improvements, culvert extensions, deck replacements, and noise barrier construction along Vincent Road in Westwood. This roadway contract will skip over the Canton/Dedham Bridge Contract (File No. 602288) involving the replacement of the Neponset River Bridge, AMTRAK/MBTA Bridge, and the University Avenue Bridge.
Location:
  • Town of Canton
  • Town of Dedham
  • Town of Randolph
  • Town of Westwood
  • Resident Engineer: Richard DeSantis
    Construction Contract Value: $57,969,727.51
    Construction Bid Price: $41,984,651.00
    Initial Construction Estimate: $46,268,356.00
    District: District 4

    Contracts (4) Progress
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 54923 -- Construction Contract
    Randolph - Westwood - Roadway Reconstruction and Related Work on a Section of Interstate 95/93 (Rte 128) Completed
    # 64307 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77860 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/07/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/04/1975
    Project Status Advertised 09/22/2007
    Project Management
    100% Design 100% Package Received 04/25/2007
    100% Design 100% Package Comments to DE 08/09/2007
    25% Design 25% Package Received 12/18/2003
    25% Design 25% Package Comments to DE 10/14/2004
    25% Design Design Public Hearing 06/29/2005
    75% Design 75% Package Received 03/06/2006
    75% Design 75% Package Comments to DE 10/04/2006
    Final Design PS&E Received 08/22/2007
    Final Design PS&E to FAPRO 09/10/2007
    Consultant Contract Process NTP Issued 04/23/2001