Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
STOUGHTON- ROADWAY RECONSTRUCTION ON SECTIONS OF TURNPIKE AND PLEASANT STREETS
Location:
  • Town of Stoughton
  • Resident Engineer: Brian Lewis
    Construction Contract Value: $7,803,095.69
    Initial Construction Estimate: $6,836,213.00
    District: District 5

    Contracts (4) Progress
    # 54619 -- Design -- Geotechnical
    Work will consist of laboratory and field testing, subsurface investigation inspection and design and analysis of complex foundation rehabilitation projects. Final
    # 57728 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 97503 -- Construction Contract
    Roadway Reconstruction on Section of Turnpike and Pleasant Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/23/1997
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 11/23/1996
    Project Management