Project Description:
ABINGTON- ROADWAY RECONSTRUCTION AND RELATED WORK ON ROUTE 18 FROM ROUTE 139 TO THE WHITMAN T.L.
This project will result in the reconstruction of Route 18 in Abington from the Abington/Whitman Town Line to approximately 350 feet south of Route 139, a distance of approximately 2.4 miles. The project includes drainage upgrades, traffic signal and traffic sign installations, pavement marking applications, landscaping, highway guardrails, driveway apron reconstruction, and water supply alterations. Also included are the construction of walls, stairs, sidewalks, wheelchairs ramps, and curbs.
Location:
  • Town of Abington
  • Resident Engineer: Robert Fitzgerald
    Construction Contract Value: $4,746,521.21
    Construction Bid Price: $3,389,839.40
    Initial Construction Estimate: $2,620,448.00
    District: District 5

    Contracts (2) Progress
    # 33222 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Route 18. Completed
    # 43147 -- Design -- Services
    Weymouth to Abington - Widening Route 18 from two to four lanes; environmental documentation and 25% design Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/05/2003
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/28/2002
    Project Management