Project Description:
BELCHERTOWN- IMPROVEMENTS & RELATED WORK ON ROUTES 202 & 21, FROM TURKEY HILL ROAD TO SOUTH MAIN STREET (1.2 MILES)
This is a complete streets project that will improve accommodations for all users. The roadway will be resurfaced and widened for improved bicycle accommodations, new and reconstructed sidewalks are proposed for improved pedestrian access, and new wheelchair ramps and crosswalks will be installed. Intersection improvements at Stadler/Front streets. Improvements will include turn lanes and possible new traffic signal.
Location:
  • Town of Belchertown
  • Design Responsibility: Municipality
    Construction Begins: Autumn 2019
    Project Manager: Albert Miller
    Estimated Total Federal Participating Construction Cost: $5,114,260.68
    Estimated Total Contract Cost: $5,603,515.95
    Funding Provision: This project is planned to be funded through the 2019 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: 100% Package Comments to DE (as of 02/26/2019 )

    Contracts (0) Status
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2019
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: BELCHERTOWN
    Category: Advertised Projects Constr.
    Budget Section: UNK

  • Construciton / (YOE $5,143,503 STP) / 59 TEC / 25% STP - 75% Due May 27, 2018
  • Category Surface Transportation Program
    Federal Cost: $4,114,802.40
    State Cost: $1,028,700.60
    Total Cost: $5,143,503.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/08/2016
    Project Initiation Form PIF Entered 01/27/2016
    Project Initiation Form PRC Submitted 01/27/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Management
    100% Design 100% Package Received 01/14/2019
    100% Design 100% Package Comments to DE 02/26/2019
    25% Design 25% Package Received 05/17/2017
    25% Design 25% Package Comments to DE 12/21/2017
    25% Design Design Public Hearing 01/10/2018
    75% Design 75% Package Received 05/04/2018
    75% Design 75% Package Comments to DE 08/22/2018