Project Description:
UPTON- CULVERT REPLACEMENT, MILFORD STREET (ROUTE 140) OVER UNNAMED TRIBUTARY TO CENTER BROOK
Existing dual culvert crossing (30" and 48" diameters), to be replaced with a 6'wx5'hx64'l box culvert. Associated drainage improvements and utility relocations.
Location:
  • Town of Upton
  • Construction Begins: Winter 2025/2026
    Resident Engineer: Peter Kurt
    Construction Bid Price: $1,828,369.50
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3

    Contracts (3) Progress
    # 115750 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 133273 -- Construction Contract
    Culvert Replacement, Milford Street (Route 140) over Unnamed Tributary to Center Brook
    # 66239 -- Design -- Services
    Work will consist of on-call environmental work on various individual projects that will vary from roadway projects to major projects identified under the Accelerated Transpor Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/02/2026
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: UPTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $2,554,355, Design Status = 75%, PM Score = 9 out of 27
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $2,043,484.00
    State Cost: $510,871.00
    Total Cost: $2,554,355.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/29/2016
    Project Initiation Form PIF Entered 01/29/2016
    Project Initiation Form PRC Submitted 01/29/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 12/27/2025
    Project Management
    100% Design 100% Package Received 07/22/2025
    100% Design 100% Package Comments to DE 09/02/2025
    100% Design 100% Plans Complete 09/19/2025
    25% Design 25% Package Received 12/13/2023
    25% Design 25% Package Comments to DE 02/26/2024
    25% Design Design Public Hearing 08/28/2024
    25% Design 25% Plans Complete 03/22/2024
    75% Design 75% Package Received 12/05/2024
    75% Design 75% Package Comments to DE 01/06/2025
    Final Design PS&E Received 10/14/2025
    Final Design PS&E to FAPRO 12/11/2025