Project Description:
TAUNTON- BRIDGE REPLACEMENT, T-01-024, SCADDING STREET OVER SNAKE RIVER
Location:
  • City of Taunton
  • Construction Begins: Autumn 2025
    Resident Engineer: Jason Vigers
    Construction Bid Price: $11,024,011.00
    District: District 5

    Contracts (3) Progress
    # 131225 -- Construction Contract
    Bridge Replacement, T-01-024, Scadding Street over Snake River
    # 77857 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77858 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/03/2025
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/07/2016
    Project Initiation Form PIF Entered 06/07/2016
    Project Initiation Form PRC Submitted 06/07/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 07/12/2025
    Project Management
    100% Design 100% Package Received 02/09/2024
    100% Design 100% Package Comments to DE 03/21/2024
    25% Design 25% Package Received 06/12/2019
    25% Design 25% Package Comments to DE 12/03/2020
    25% Design 25% Package Rejected 01/22/2020
    25% Design 25% Package Received - Resub 1 09/03/2020
    25% Design Design Public Hearing 06/08/2021
    75% Design 75% Package Received 07/01/2021
    75% Design 75% Package Comments to DE 10/01/2021
    75% Design 75% Package Received - Resub 1 09/29/2022
    Final Design PS&E Received 05/24/2024
    Final Design PS&E Received - Resub 1 08/22/2024
    Final Design PS&E Received - Resub 2 01/17/2025
    Final Design PS&E Received - Resub 3 03/07/2025
    Final Design PS&E Received - Resub 4 03/28/2025
    Consultant Contract Process Scope to DE 05/01/2017
    Consultant Contract Process NTP Issued 05/31/2017
    Consultant Contract Process Workhours Approved 05/12/2017