ORLEANS- INTERSECTION IMPROVEMENTS AT ROUTE 28 (SOUTH ORLEANS ROAD), ROUTE 39 (HARWICH ROAD) AND QUANSET ROAD
Work on this project consists of the installation of a roundabout along with associated geometric improvements. ADA compliant sidewalks are proposed within the project limits.
Location:
  • Town of Orleans
  • Construction Begins: Summer 2022
    Resident Engineer: Ian Bettencourt
    Construction Bid Price: $5,714,897.75
    District: District 5

    Contracts (1) Progress
    # 118041 -- Construction Contract
    Intersection Improvements and Related Work Route 28 (South Orleans Road) at Route 39 (Harwich Road) and Quanset Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/01/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/26/2016
    Project Initiation Form PIF Entered 09/14/2016
    Project Initiation Form PRC Submitted 09/23/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Status Advertised 05/21/2022
    Project Management
    100% Design 100% Package Received 05/17/2021
    100% Design 100% Package Comments to DE 06/18/2021
    25% Design 25% Package Received 04/23/2018
    25% Design 25% Package Comments to DE 02/08/2019
    25% Design Design Public Hearing 12/11/2019
    75% Design 75% Package Received 09/01/2020
    75% Design 75% Package Comments to DE 12/08/2020
    Final Design PS&E Received 09/29/2021
    Final Design PS&E Received - Resub 1 01/26/2022
    Final Design PS&E Received - Resub 2 04/28/2022