Project Description:
BOURNE TO BRAINTREE- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF ROUTE 3
This project will replace existing guide and traffic signs with new signs mounted on new and existing supports on State Route 3 between Exit 1 in Bourne and Exit 43 in Braintree, including applicable signs on intersecting secondary roads.
Location:
  • Town of Bourne
  • Town of Braintree
  • Town of Duxbury
  • Town of Hanover
  • Town of Hingham
  • Town of Kingston
  • Town of Marshfield
  • Town of Norwell
  • Town of Pembroke
  • Town of Plymouth
  • Town of Rockland
  • Town of Weymouth
  • Construction Begins: Winter 2024/2025
    Resident Engineer: Trevor O'Bryan
    Construction Bid Price: $2,827,066.50
    District: District 5
    Current Status: • Environmental walk was done on 4/8/26. • Advanced warning signs were installed on 4/9/26. • Clearing and tree removal started on 4/20/26. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM (as of 05/11/2026)

    Contracts (1) Progress
    # 128751 -- Construction Contract
    Guide and Traffic Sign Replacement on a Section of Route 3 33% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/11/2025
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    • Environmental walk was done on 4/8/26. • Advanced warning signs were installed on 4/9/26. • Clearing and tree removal started on 4/20/26. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/05/2020
    Project Initiation Form PIF Entered 03/05/2020
    Project Initiation Form PRC Submitted 03/05/2020
    Project Review Committee PRC Approved 03/06/2020
    Project Status Advertised 11/16/2024
    Project Management
    100% Design 100% Package Received 12/18/2023
    75% Design 75% Package Received 12/18/2023
    Final Design PS&E Received 07/22/2024
    Final Design PS&E to FAPRO 10/31/2024
    Consultant Contract Process Scope to DE 06/30/2022