BOURNE- SANDWICH- RESURFACING AND RELATED WORK ON ROUTE 6
Location:
  • Town of Bourne
  • Construction Begins: Spring 2025
    Resident Engineer: Gabriel Rodrigues
    Construction Bid Price: $7,642,386.00
    District: District 5
    Current Status: Contractor has acquired field office and submitted commencement submittals. Contractor has ongoing work, cleaning and adjusting drainage structures, and installing erosion control. Scheduled work hours are Sunday through Friday, 9:00 PM to 5:00 AM. Expect periodic lane closures and restrictions. (as of 10/17/2025)

    Contracts (1) Progress
    # 129789 -- Construction Contract
    Resurfacing and Related Work on Route 6 1% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/11/2025
    Contract Information
    Project Designer:
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractor has acquired field office and submitted commencement submittals. Contractor has ongoing work, cleaning and adjusting drainage structures, and installing erosion control. Scheduled work hours are Sunday through Friday, 9:00 PM to 5:00 AM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/24/2021
    Project Initiation Form PIF Approved 02/24/2021
    Project Initiation Form PRC Submitted 03/01/2021
    Project Review Committee PRC Approved 03/26/2024
    Project Status Advertised 03/22/2025
    Project Management
    100% Design 100% Package Received 12/16/2024
    25% Design 25% Package Received 08/26/2024
    75% Design 75% Package Received 08/26/2024
    Final Design PS&E Received 12/16/2024
    Final Design PS&E Received - Resub 1 02/14/2025