| Project Description: |
DISTRICT 5- CLEANING AT BRIDGE LOCATIONS ALONG THE I-495 CORRIDOR
|
| Location: | |
| Construction Begins: | Winter 2023/2024 |
| Resident Engineer: | Michael Horton![]() |
| Construction Bid Price: | $1,615,370.00 |
| District: | District 5 |
| Current Status: | - Remaining Bridge seat/deck joint washing & cleaning to be completed at part of punchlist work when weather allows (<5%) - All pvc deck drain extension work has been completed Normal work hours are Sunday through Thursday, 9:00 PM to 5:30 AM Scheduled work hours are 9:00PM through 5:30AM Expect periodic lane closures and restrictions. (as of 03/05/2026) |
| Additional Info: | Contractor has temporarily de-mobilized from contract work. Punchlist will be completed when weather allows. (as of 03/05/2026) |
|