DISTRICT 3- SCHEDULED & EMERGENCY BRIDGE STRUCTURAL & SUBSTRUCTURE REPAIRS AND RELATED WORK AT VARIOUS LOCATIONS ALONG I-90
Location:
Construction Begins: Spring 2023
Resident Engineer: Yasser Talib
Construction Bid Price: $1,661,270.00
District: District 3

Contracts (1) Progress
# 121953 -- Construction Contract
Scheduled & Emergency Bridge Structural & Substructure Repairs and Related Work at Various Locations along I-90 37% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/21/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/20/2023
    Project Initiation Form PIF Entered 01/20/2023
    Project Initiation Form PRC Submitted 01/20/2023
    Project Review Committee PRC Approved 01/27/2023
    Project Status Advertised 04/29/2023
    Project Management
    100% Design 100% Package Received 02/21/2023
    100% Design 100% Package Comments to DE 03/28/2023
    Final Design PS&E Received 04/03/2023