Project Description:
DISTRICT 5- SCHEDULED AND EMERGENCY SUBSTRUCTURE REPAIRS AT VARIOUS LOCATIONS
The work under this Project shall consist of performing scheduled and emergency bridge substructure work on bridges in District 5.
Location:
Construction Begins: Autumn 2023
Resident Engineer: Michael Horton
Construction Bid Price: $2,945,474.00
District: District 5
Current Status: - MIG will look to mobilize to next Work Order Location: South Street over Rt-3 in Norwell to begin work on 7/8/25 Normal work hours are Monday thru Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 07/07/2025)

Contracts (1) Progress
# 124350 -- Construction Contract
Scheduled and Emergency Substructure Repairs at Various Locations 69% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/12/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    - MIG will look to mobilize to next Work Order Location: South Street over Rt-3 in Norwell to begin work on 7/8/25 Normal work hours are Monday thru Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/26/2023
    Project Need Form PNF Approved 01/26/2023
    Project Initiation Form PIF Entered 01/26/2023
    Project Initiation Form PIF Approved 01/26/2023
    Project Initiation Form PRC Submitted 01/27/2023
    Project Review Committee PRC Approved 01/30/2023
    Project Status Advertised 10/14/2023
    Project Management
    100% Design 100% Package Received 06/29/2023
    100% Design 100% Package Comments to DE 07/25/2023
    Final Design PS&E Received 08/07/2023
    Final Design PS&E Received - Resub 1 09/01/2023