Project Description:
WESTPORT- BRIDGE PRESERVATION OF W-30-025 (3UD, 3UE), I-195 OVER SANFORD ROAD
Location:
  • Town of Westport
  • Construction Begins: Autumn 2024
    Resident Engineer: Dylan Hipolito
    Construction Bid Price: $1,843,832.25
    District: District 5
    Current Status: The contractor has completed the hydro-demolition operation on eastbound and westbound bridge decks I-195. On-going work consists of bridge deck shielding, full and partial depth bridge deck repairs, and substructure concrete repairs. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Scheduled work hours are 7:00 PM to 5:00 AM. Expect periodic lane closures and restrictions. (as of 06/17/2025)

    Contracts (1) Progress
    # 127515 -- Construction Contract
    Bridge Preservation of W-30-025 (3UD, 3UE), I-195 over Sanford Road

    Bridges

    Contract Dates
    Notice to Proceed: 10/04/2024
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The contractor has completed the hydro-demolition operation on eastbound and westbound bridge decks I-195. On-going work consists of bridge deck shielding, full and partial depth bridge deck repairs, and substructure concrete repairs. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Scheduled work hours are 7:00 PM to 5:00 AM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/03/2023
    Project Need Form PNF Approved 04/03/2023
    Project Initiation Form PIF Entered 04/03/2023
    Project Initiation Form PIF Approved 04/03/2023
    Project Initiation Form PRC Submitted 04/03/2023
    Project Review Committee PRC Approved 04/12/2023
    Project Status Advertised 08/03/2024
    Project Management
    75% Design 75% Package Received 04/16/2024
    75% Design 75% Package Comments to DE 05/31/2024
    Final Design PS&E Received 06/14/2024
    Final Design PS&E Received - Resub 1 07/11/2024