Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 1- APPLICATION OF REFLECTORIZED PAVEMENT MARKINGS AT VARIOUS LOCATIONS
Maintain pavement markings on State Highway.
Location:
Construction Begins: Summer 2025
Resident Engineer: Jose Arias Batista
Construction Bid Price: $309,780.00
District: District 1

Contracts (1) Progress
# 130182 -- Construction Contract
Application of Reflectorized Pavement Markings at Various Locations 32% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/01/2025
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/25/2024
    Project Need Form PNF Approved 04/25/2024
    Project Initiation Form PIF Entered 04/25/2024
    Project Initiation Form PIF Approved 04/25/2024
    Project Initiation Form PRC Submitted 05/23/2024
    Project Review Committee PRC Approved 05/31/2024
    Project Status Advertised 05/03/2025
    Project Management
    100% Design 100% Package Received 04/04/2025
    Final Design PS&E Received 04/04/2025
    Final Design PS&E to FAPRO 04/14/2025