DISTRICT 3- DEPLOYMENT OF TEMPORARY TRAFFIC CONTROL AT VARIOUS LOCATIONS
This project will consist of a vendor providing traffic management support to bridge maintenance and bridge inspection operations.
Location:
Construction Begins: Spring 2025
Resident Engineer: Mahmood Azizi
Construction Bid Price: $353,462.00
District: District 3

Contracts (1) Progress
# 129557 -- Construction Contract
Deployment of Temporary Traffic Control at Various Locations 45% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/11/2025
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/22/2024
    Project Initiation Form PIF Entered 06/22/2024
    Project Initiation Form PRC Submitted 06/22/2024
    Project Review Committee PRC Approved 06/25/2024
    Project Status Advertised 02/22/2025
    Project Management
    100% Design 100% Package Received 12/02/2024
    Final Design PS&E Received 12/02/2024
    Final Design PS&E to FAPRO 12/04/2024