Project Description:
LEVERETT- BRIDGE REHABILITATION, L-09-011, ROUTE 63 (LONG PLAIN ROAD) OVER NEW ENGLAND CENTRAL RAILROAD (NECRR)
The work under this project consists of replacing the Route 63 (Long Plain Road) Bridge over the NEC RR. The proposed structure will be a three-span steel beam reinforced concrete deck structure with new stub abutments. The approach roadways will be reconstructed to achieve the required minimum vertical railroad clearances by raising the profile. The new bridge will be constructed in stages on a new horizontal alignment to the west. A temporary traffic signal will be installed to manage the alternating flow of traffic during construction. A new concrete sidewalk will be constructed on the south side of the bridge.
Location:
  • Town of Leverett
  • Resident Engineer: William Whiteman
    Construction Contract Value: $6,521,548.00
    Construction Bid Price: $5,585,662.00
    Initial Construction Estimate: $5,153,929.00
    District: District 2

    Contracts (3) Progress
    # 32181 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract N Final
    # 56515 -- Construction Contract
    Leverett - Bridge Replacement (L-09-011) Route 63 (Long Plain Road) over New England Central Railroad Completed
    # 57732 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects, includes ABP projects Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/17/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/31/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 01/06/2003
    Project Status Advertised 07/05/2008
    Project Management
    100% Design 100% Package Received 12/19/2007
    100% Design 100% Package Comments to DE 01/31/2008
    25% Design 25% Package Received 09/15/2005
    25% Design 25% Package Comments to DE 11/21/2005
    25% Design Design Public Hearing 03/23/2006
    75% Design 75% Package Received 11/29/2006
    75% Design 75% Package Comments to DE 11/28/2007
    Final Design PS&E Received 06/04/2008
    Final Design PS&E to FAPRO 06/27/2008
    Consultant Contract Process NTP Issued 02/04/2003